•   Recall and replace 100 laptops that are coming off lease
•    Install 180 desktops in labs throughout the Valley; the in-house development of new systems for managing and maintaining PC configurations and software tracking will significantly streamline these installations
•    In July - begin hiring IT Services Monitors for the fall
•    Install the Landmark and St. Paul computers, as well as moving many other labs, International Education and Faculty offices, into the new Centre for Learning
•    Move into the new Ed Tech Centre space in the Centre for Learning
•    The main floor of the Library where the current IT KLO space is located will be renovated over the summer; Help Desk will be moved to open into the atrium
•    Decommission the portables on the KLO Road campus and move one of them to the Penticton Campus
•    Move the Penticton portables in preparation for their recently announced building projects
•    Install voice and data wiring in the new Aboriginal Centre in Salmon Arm
•    Complete 70 Audio Visual installs including 22 classrooms and 10 meeting rooms in the Centre for Learning
•    Telecommunications is installing the cabling to the new building and will be completing the voice and data wiring in May and June in preparation for faculty and staff moves over the summer
•    Rollout the new People directory (formerly, Staff Directory)
•    Rollout a new Service Request for Account Creation for new and transferring personnel
•    Rollout the new on-line transcript request
•     Eight IT personnel  will attend IT4BC in late May; OC has taken on two Track Chair responsibilities and will present  four  workshops  at the annual conference which is hosted this year, by VCC
•    Several people will attend the first BC Banner User Group meeting in Victoria
•    One person will attend the Educause Institute Management Program
•    There will be summer long preparation and testing for the Banner 8 upgrade which is planned for  the Thanksgiving weekend in the fall  (btw, OC started on Banner 2.0 in 1996)
•    Review a new editor for use on our website 
•    Regional Campus Technicians will be busy with laptop upgrades and computer lab installations
•    Upgrade to Blackboard 8.0 (myCourses)
•    Build a new, shared communication centre/secondary data centre to address future communications and business continuity initiatives